STRESS TEST
Before the test meal:
- switch all cages to the active passive mode
- change intensity in the feeding system before meal start
📋 Steps
Feeding control via
...
a Feeding system
- 1. Cage 1: Start feeding -->> Flush a pipe for a minute -> confirm that the blower has started.we do receive blower level
- 2. Cage 21: Wait ->confirm that the feeding is started and that we do receive the feeding data
we should get the intensity that has been set before feeding. - 3. Cage 1: Change the intensity during pipe flush -> confirm that the feeding is not started in Feeding System.
- 3. Start a meal with 1 kg/min intensity -> confirm that feed spreader started.
- we do receive intensity changes and they are reflected in FA4 UI
- 4. Cage 1: Stop feeding -> confirm that the meal is stopped in 5 min on FA4